Bill of Material (BOM)
The components that you need for manufacturing a Product (Finished Good) will be defined in a structured manner with the step wise sequence of operation. What has to be manufactured first and what next, the number of components, Resource (Machine and Technical Labour ) that we require to manufacture a Product will be defined in Oracle Bill Of Material
Work in Process (WIP)
Work-in-process (WIP) has two different meanings. One that describes the physical state of the inventory, and another that describes an account used to track the value of work-in-process.
--------------------------------------------------------------------------------------------------------------------
SETUP CONFIGURATION
BOM SETUPS
A bill of materials (BOM) is a comprehensive inventory of the raw materials, assemblies, subassemblies, parts and components, as well as the quantities of each, needed to manufacture a product. In a nutshell, it is the complete list of all the items that are required to build a product....more
WIP SETUPS
Oracle WIP module facilitates in creating WIP job or work order to manufacture the goods.
Discrete Job or Work In Process (WIP) Job is a work order issued to shop floor to manufacture or assemble an item...more
OSP SETUPS
The semifinished/finished product is sent to the Subcontractor/ External Vendor to perform the packing process and return it back to the warehouse team. The material will be directly sent to the shop floor instead of maintaining it in the inventory.....more
-----------------------------------------------------------------------------------------------------------
Transaction Process Flow
1. Standard Job Creation
Standard Job order
Predefined Resource & Component Allocation
It control the material, resources, and operations required to build an assembly
When there is no change in process flow...more
2. Outside Processing [OSP]
Outside Processing (OSP) is a subcontracting process where certain operations in a process routing are performed by the subcontractor. This process can be leveraged by manufacturers who do not always have the capabilities or equipment to perform all the steps in their manufacturing process to produce their products.
Non-availability of machine or large production time we going to use the outsourcing functionality....more
3. Non-Standard Job Creation
Non-Standard Job Order
Manual Resource & Component Allocation
It control material and collect costs for miscellaneous manufacturing activity
Eg. Rework, field service repair, upgrade, disassembly, maintenance
This type is applicable for custom Jobs orders...more