 Navigation: Production Supervisor : Setup : Parameters


Define the process execution parameters
 Allow Material Deletion: It means system will allow you to delete the items in Pending & WIP status only as per the setup. But once the actual quantity is transacted system will not allow to delete the items.

 Default Actual Resource Usage : The Step quantity will be defaulted as resource actual usage as per this setup
 Based on the document number setup batch number will be created during the batch creation
 In case if the Ingredient Consumption Type is setup as Automatic then material will be consumed from the supply sub inventory for WIP Issue and product will be receipted against the yield sub inventory for WIP Completion.
Based on this setup OSP process works. When the requisition will be created either manual or at Batch release or Batch creation or at Step Release.